The synchronous technology of pushing and assembling shield machine was successfully tested in Shanghai

This is the "Jiyue" shield machine in the workshop of Shanghai Tunnel Machinery Manufacturing Branch (photo taken on April 13, drone photo).

The synchronous technology of shield tunneling and assembling independently developed by Shanghai Tunnel Engineering Co., Ltd. has been successfully tested recently, and the first push-and-assemble synchronous shield machine is about to go offline. In the process of tunnel construction, the shield machine using this technology will realize the parallel operation of tunneling and assembly, which will greatly improve the construction efficiency.

In the traditional shield machine construction, the construction process is generally advancing, stopping and assembling. Every time the shield machine goes forward, it needs to stop in situ, complete the assembly of a segment, and then continue the excavation. Tunnel excavation and segment assembly are carried out in series. The parallel operation of excavation and assembly can be realized by applying the push-and-push synchronization technology. Relevant simulation tests show that the push-and-push synchronization technology will greatly reduce the operation time of each ring segment of shield machine and improve the construction efficiency by 30% to 50%.

Xinhua News Agency reporter Fang Yushe

A worker uses a waist-hanging remote control to operate and test the push-and-pull synchronous assembly of the "Jiyue" shield machine (photo taken on April 13).

The synchronous technology of shield tunneling and assembling independently developed by Shanghai Tunnel Engineering Co., Ltd. has been successfully tested recently, and the first push-and-assemble synchronous shield machine is about to go offline. In the process of tunnel construction, the shield machine using this technology will realize the parallel operation of tunneling and assembly, which will greatly improve the construction efficiency.

In the traditional shield machine construction, the construction process is generally advancing, stopping and assembling. Every time the shield machine goes forward, it needs to stop in situ, complete the assembly of a segment, and then continue the excavation. Tunnel excavation and segment assembly are carried out in series. The parallel operation of excavation and assembly can be realized by applying the push-and-push synchronization technology. Relevant simulation tests show that the push-and-push synchronization technology will greatly reduce the operation time of each ring segment of shield machine and improve the construction efficiency by 30% to 50%.

Xinhua News Agency reporter Fang Yushe

This is the "Jiyue" shield machine in the workshop of Shanghai Tunnel Machinery Manufacturing Branch (photo taken on April 13th).

The synchronous technology of shield tunneling and assembling independently developed by Shanghai Tunnel Engineering Co., Ltd. has been successfully tested recently, and the first push-and-assemble synchronous shield machine is about to go offline. In the process of tunnel construction, the shield machine using this technology will realize the parallel operation of tunneling and assembly, which will greatly improve the construction efficiency.

In the traditional shield machine construction, the construction process is generally advancing, stopping and assembling. Every time the shield machine goes forward, it needs to stop in situ, complete the assembly of a segment, and then continue the excavation. Tunnel excavation and segment assembly are carried out in series. The parallel operation of excavation and assembly can be realized by applying the push-and-push synchronization technology. Relevant simulation tests show that the push-and-push synchronization technology will greatly reduce the operation time of each ring segment of shield machine and improve the construction efficiency by 30% to 50%.

Xinhua News Agency reporter Fang Yushe

This is the "Jiyue" shield machine in the workshop of Shanghai Tunnel Machinery Manufacturing Branch (photo taken on April 13th).

The synchronous technology of shield tunneling and assembling independently developed by Shanghai Tunnel Engineering Co., Ltd. has been successfully tested recently, and the first push-and-assemble synchronous shield machine is about to go offline. In the process of tunnel construction, the shield machine using this technology will realize the parallel operation of tunneling and assembly, which will greatly improve the construction efficiency.

In the traditional shield machine construction, the construction process is generally advancing, stopping and assembling. Every time the shield machine goes forward, it needs to stop in situ, complete the assembly of a segment, and then continue the excavation. Tunnel excavation and segment assembly are carried out in series. The parallel operation of excavation and assembly can be realized by applying the push-and-push synchronization technology. Relevant simulation tests show that the push-and-push synchronization technology will greatly reduce the operation time of each ring segment of shield machine and improve the construction efficiency by 30% to 50%.

Xinhua News Agency reporter Fang Yushe

Two workers were running and debugging the "Jiyue" shield machine in the workshop (photo taken on April 13).

The synchronous technology of shield tunneling and assembling independently developed by Shanghai Tunnel Engineering Co., Ltd. has been successfully tested recently, and the first push-and-assemble synchronous shield machine is about to go offline. In the process of tunnel construction, the shield machine using this technology will realize the parallel operation of tunneling and assembly, which will greatly improve the construction efficiency.

In the traditional shield machine construction, the construction process is generally advancing, stopping and assembling. Every time the shield machine goes forward, it needs to stop in situ, complete the assembly of a segment, and then continue the excavation. Tunnel excavation and segment assembly are carried out in series. The parallel operation of excavation and assembly can be realized by applying the push-and-push synchronization technology. Relevant simulation tests show that the push-and-push synchronization technology will greatly reduce the operation time of each ring segment of shield machine and improve the construction efficiency by 30% to 50%.

Xinhua News Agency reporter Fang Yushe

Workers observe the mechanical operation under the push-and-push synchronous assembly of the "Jiyue" shield machine (photo taken on April 13).

The synchronous technology of shield tunneling and assembling independently developed by Shanghai Tunnel Engineering Co., Ltd. has been successfully tested recently, and the first push-and-assemble synchronous shield machine is about to go offline. In the process of tunnel construction, the shield machine using this technology will realize the parallel operation of tunneling and assembly, which will greatly improve the construction efficiency.

In the traditional shield machine construction, the construction process is generally advancing, stopping and assembling. Every time the shield machine goes forward, it needs to stop in situ, complete the assembly of a segment, and then continue the excavation. Tunnel excavation and segment assembly are carried out in series. The parallel operation of excavation and assembly can be realized by applying the push-and-push synchronization technology. Relevant simulation tests show that the push-and-push synchronization technology will greatly reduce the operation time of each ring segment of shield machine and improve the construction efficiency by 30% to 50%.

Xinhua News Agency reporter Fang Yushe

This is the "Jiyue" shield machine in the workshop of Shanghai Tunnel Machinery Manufacturing Branch (photo taken on April 13th).

The synchronous technology of shield tunneling and assembling independently developed by Shanghai Tunnel Engineering Co., Ltd. has been successfully tested recently, and the first push-and-assemble synchronous shield machine is about to go offline. In the process of tunnel construction, the shield machine using this technology will realize the parallel operation of tunneling and assembly, which will greatly improve the construction efficiency.

In the traditional shield machine construction, the construction process is generally advancing, stopping and assembling. Every time the shield machine goes forward, it needs to stop in situ, complete the assembly of a segment, and then continue the excavation. Tunnel excavation and segment assembly are carried out in series. The parallel operation of excavation and assembly can be realized by applying the push-and-push synchronization technology. Relevant simulation tests show that the push-and-push synchronization technology will greatly reduce the operation time of each ring segment of shield machine and improve the construction efficiency by 30% to 50%.

Xinhua News Agency reporter Fang Yushe

1111.jpg